Regulation (EU) 2019/943 Roadmap

DEC 2022

Decision on the adoption of the new electricity package

DEC 2022

No capacity mechanisms for new generation with >550g CO2/kWh (Article 22)

JAN 2023

Imbalance settlement period shall be 15min1 (Article 8)

Contracting Parties to report on measures to prevent wholesale price limitation (Article 10)

DEC 2023

Regulation (EU) 2019/943 transposition deadline

DEC 2023

Establishment of system operation regions (Annex V)

Establishment of regional coordination centres (Annex IV)

TSOs to provide 70% cross-zonal capacity2 (Article 16)

Existing capacity mechanisms to be compliant with the Regulation (Article 22)

JUN 2024

TSOs to participate in regional coordination centres (Article 36)

Regional coordination centres to present proposal on their set-up (Annex IV)

JUL 2025

No capacity mechanisms for new generation with >550g CO2/kWh and >350kg CO2/y/kWe (Article 22)

DEC 2025

Bidding zone review for Contracting Parties3 (Article 14)

1 unless derogation is granted (latest Dec 24) 
2 unless derogation is granted/action plan is applied (latest Jan 28) 
3 6 months after ENTSO-E report on congestions or latest Dec 25