Risk-preparedness Regulation (EU) 2019/941 Roadmap

NOV 2021

Decision on adoption of internal electricity market acts

MAY 2022

ENTSO-E to define regional crisis scenarios (Article 6)

SEP 2022

Contracting Parties to define national crisis scenarios(Article 7)

DEC 2022

Decision on the adoption of a recast in line with the new electricity package

JAN 2023

Contracting Parties to designate competent authority (Article 3)

DEC 2023

Regulation (EU) 2019/941 transposition deadline

JAN 2025

Competent authority to adopt and publish first risk preparedness plan (Article 10)

Read more
SEP 2028

The Secretariat to evaluate the possible means by which to enhance security of electricity supply at the Energy Community level (Article 18)

1 to be delivered 4 months after regional scenarios