Gas_15 / Firm Reverse flow: Beregdaróc (HU) - Beregovo (UA)

Brief project description

Ukrtransgaz: ensuring non interruptible capacity from HU>UA border- Beregovo (UA) existing DN800 pipeline, transmission further on the existing pipeline system.

FGSZ: Contribution to security of supply. The main aim of studied expansion is ensuring non interruptible capacity at the existing Beregdaróc DN800 (Beregdaróc- HU>UA border). The project contributes to the creation of the gas evacuation route for the gas delivered to the LNG terminal in Krk, which recently received financing from the European Commission. The maximum capacity in case of HU>UA direction deliveries can be 16.8 Mcm/d; 700,000 cm/h. HU>UA exit volume can be delivered to Beregdaróc 700,000 cm/h partially or entirely:
from Városföld - Hajdúszoboszló direction,
from Zsámbok - Nemesbikk direction,
from DN1400, PN75 pipeline from Ukraine.