CASE NO. ECS 12/11

29 Nov 2011

Secretariat sends Opening Letter to Montenegro concerning the lack of cost-reflectivity of distribution network tariff

On 28 November 2011, the Secretariat sent an Opening Letter to Montenegro in accordance with Article 12 of the Rules of Procedure for Dispute Settlement. The Secretariat takes the preliminary view that Montenegro failed to fulfill its obligations under the Energy Community Treaty by its regulatory authority setting distribution network tariffs not fully in line with the principle of cost-reflectivity.

 

Cost-reflectivity of network tariffs is a precondition for the viability of these networks and ultimately for attracting investment and securing energy supply, both of which are key objectives of the Energy Community Treaty. The principle of cost-reflectivity is embedded in the Energy Community acquis communautaire. In the Secretariat’s position as expressed in the Opening Letter, deviations are possible if they are motivated by the wish to increase the efficiency of operating the network, and comply with the general principles of Energy Community law such as legal certainty or the duty to provide reasons.

 

The present case concerns the Montenegrin regulatory authority’s decision to set the distribution network tariff in electricity for 2011/2012. More precisely, the Opening Letter considers the manner of how certain cost-factors have been determined, but not the appropriateness of concrete figures, which is a task for the regulatory authority alone. The Secretariat identified the setting of the level of recognized network losses, the costs for procurement of the electricity necessary to cover network losses and the rate of return on assets as problematic from the perspective of cost-reflectivity.

 

With regard to the level of network losses recognized by the regulatory authority, the decision is flawed, in the Secretariat’s view, by the refusal to take into account any losses other than technical. This excludes all so-called commercial losses, a denomination normally used for electricity thefts. As regards the amounts accepted by the regulatory authority for the costs of electricity used to cover the losses, as well as the rate of return on assets set by the regulatory authority, the Secretariat essentially challenges the lack of reasoning of the concrete findings in the decision. Instead, the decision is based extensively on the regulatory authority’s discretion, given to it by the Energy Law, to contain costs in order to “limit the growth of prices and tariffs for the purpose of achieving the economic and energy policy of Montenegro”. It does not become clear in the decision to what extent the viability of the networks has been taken into account in those considerations.

 

By sending an Opening Letter, the Secretariat initiates a preliminary procedure, the purpose of which is giving the Party concerned the possibility, within two months, to react to the allegation of non-compliance with Energy Community law, and enabling the Secretariat to establish the full background of the case.

 

According to Articles 6 and 16 of the Rules of Procedure for Dispute Settlement, interested parties may be granted access to the case file and may submit written observations on the present case to the Secretariat within one month from today. 

 

All requests for information on this case should be addressed to the Legal Counsel at dirk.buschle@energy-community.org or +43 1 535 2222 24 and should make reference to the case number ECS-12/11.

 

 back|top